Construction Update (February 14, 23)

It’s been a bit since the last update. A few things have transpired.

First!, it turns out we needed a bit more flooring than we ordered. Oops! Due to shipping delays and product availability, it only arrived last week.

Second, our double oven for the front part of our space didn’t quite align with the cabinet we bought. The contractors have been great. Through some creative engineering and proper supports we were able to modify the cabinet to support the oven.

We’re loving the cabinets and countertop! Once things are seal and finished up everything is going to look really great.

A final coat of paint will be going on the walls this week. We’ll also be closing up the utility closet and finalizing the equipment layout. We can’t wait to open soon!